PayeshCo | National Oil Transmission Pipeline 
Back to archive
File · 2021 Completed — 2021

National Oil Transmission Pipeline

Corrosion monitoring and DCVG/CIPS surveys over hundreds of kilometres of buried pipeline.

National Oil Transmission Pipeline
320 km buried line
  1. 01 Client NIOPDC
  2. 02 Location South–Central corridor
  3. 03 Year 2021
  4. 04 Scopes Corrosion Monitoring Cathodic Protection
Field gallery 3 frames

Challenge

Localized corrosion at river crossings and AC interference from co-located power lines. Legacy survey data was fragmented without integrated GIS mapping.

Solution

High-resolution DCVG, continuous CIPS, and AC/DC interference analysis. Corrosion risk mapping with coating repair prioritization. Operator training for periodic monitoring.

"PayeshCo's engineering report became the basis for our annual repair program. Field accuracy and NACE SP0502 compliance were outstanding."

Dr. A. Rezaei Inspection Technical Manager — NIOPDC